Before installing the equipment of tempering furnace, please prepare the following things your factory:
1.According to the layout, blower layout, electrical layout supplied by the seller, please prepare the power joint (power supply), air joint (air supply), blower foundation, etc.
2.In order to make the installation go with a swing, please prepare the following instruments at site: Electric Welding machine, hand electric drill, air-cutting equipment, cutting machine (for cutting steels), cleaner, Pinch bar (Crowbar), Hand grinding wheel machine, double heads spanner, inner hexagonal spanner, spring clamp for hole and bearing, hand hammer, wire-cutter, acutilingual clamp, flat and cross screwdriver, wide and thin flat filing, semi-round filing, 250mm movable spanner, clamp-shape universal meter, electrical pen, etc.
3.Materials: 800# water sand paper (50 pieces), sulfur powder (1.5 kgs), CCl4 (500ml).
4. Workers as assistant: four Locksmiths, one electrician, and several normal workers. It is better if you could arrange the works who know well the equipment.
5. Sheet glass: you should prepare some pieces of sheet glass (float glass) for trial production and testing the equipment.
6. It is better that if you could supply one mobile or telephone and internet for our engineers.